SAP PP Online Quiz



Following quiz provides Multiple Choice Questions (MCQs) related to SAP PP. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Questions and Answers

Q 1 - In Material Requirement Planning, which of the following table contains document header data?

A - MDKP

B - MDTB

C - MDVM

D - MDFD

Answer : A

Explanation

MDKP Document Header data

MDTB Table Structure

MDVM Planning File Details

MDFD MRP Date details

Q 2 - In PP, which of the following is not a valid category for BOM?

A - Material BOM

B - Equipment BOM

C - Cost BOM

D - Inspection BOM

Answer : D

Answer : A

Explanation

Key Features related to Routing −

To create routing it is mandate that you first define work center.

Multiple material can follow single routing group.

Routing is used for scheduling and costing of operation for raw and finished products.

Routing is used for calculation operation cost for finished product.

Q 4 - For Make to Order process, which of the following Planning strategy is used?

A - 20

B - 25

C - 30

D - 35

Answer : A

Explanation

You use Planning strategy 20 for make to order MTO process and planning strategy 25 is used to produce product variants when there is request for variant products from customer

Q 5 - Which of the following doesn’t represent an issue Material Requirement Planning element?

A - Sales Order

B - PIR

C - Transfer Order

D - Production Order

Answer : D

Explanation

Issues include PIRs, Dependent Requirements, Order Reservations, Sales Orders, Issuing Stock Transfer Orders, etc. and receipts include Production Orders, Purchase Requisitions, Purchase Orders, Open Production Orders, Receiving Stock Transfer Order, Schedule lines, etc.

Q 6 - Using T-Code CO01, you can create a Production order without referring planned order?

A - True

B - False

Answer : A

Explanation

Q 7 - In which of MRP type, system consider all the material irrespective of changes and it is time consuming and not common in Production planning?

A - NetChange

B - NetChange in Planning horizon

C - Regenerative Planning

D - None of these

Answer : C

Explanation

NetChange

In this run system consider those material which has undergone some changes from the previous MRP run.

NetChange in planning horizon

This run considers the requirement in predefined planning horizon and not like net change which check the future requirements.

In this run, system consider only those material which has undergone some changes from their last MRP run.

Regenerative Planning

In this run, system consider all the material irrespective of changes and it is time consuming and not common in Production planning.

Q 8 - To perform Goods issue reversal, what is the movement type?

A - 261

B - 262

C - 263

D - 264

Answer : B

Q 9 - Which of the following report is used to collect information about hierarchy of work center of a shift?

A - Shift Transfer Report

B - Shift Report

C - Shift Work center Report

D - None of these

Answer : B

Q 10 - To set your PIR version active, which of the below value should be used to specify requirement would be considered in material requirement planning?

A - 00

B - 01

C - 02

D - 03

Answer : A

Explanation

In SAP PP, demand management is performed by Planned Independent requirement PIR. Planned Independent requirement provides input for production planning. A PIR contains one planned quantity of product and one date for material or a planned quantity is split over a span of time period.

To set your PIR version active use value 00 to specify requirement would be considered in material requirement planning. To maintain number of versions of planned independent requirement, you can set some numbers to active and others to inactive.

sap_pp_questions_answers.htm
Advertisements