SAP PP Online Quiz



Following quiz provides Multiple Choice Questions (MCQs) related to SAP PP. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Questions and Answers

Q 1 - In Production Planning, which of the following is first step to start Production process?

A - Production order confirmation

B - Issuing goods for production order

C - Converting planned order to Production Order

D - Issue the production order

Answer : C

Explanation

Converting planned order to Production Order −

First step is to convert a planned order to production order. When you create a Production Order, type is defined in SAP PP system.

Q 2 - In SAP Production Planning, how many BOM’s can be created as per material type?

A - 100

B - 99

C - 50

D - 49

Answer : B

Q 3 - To create routing it is mandate that you first define work center?

A - True

B - False

Answer : A

Q 4 - SAP Production Planning is integrated with which of the following modules?

A - Material Management

B - Sales and Distribution

C - Controlling

D - SAP QM

E - All of the above

Answer : E

Q 5 - Long Term Planning is not actual run but is used to see if all capacity requirement can be fulfilled and you can also transfer simulative area to operative area if requirements are fulfilled?

A - True

B - False

Answer : A

Explanation

Long term planning in SAP PP is used to check future demands at all Bill of Material level. You can check the current capacity and vendor ability to provide the material in required time period.

This is not actual run but is used to see if all capacity requirement can be fulfilled and you can also transfer simulative area to operative area if requirements are fulfilled.

Q 6 - Using T-Code CO01, you can create a Production order without referring planned order?

A - True

B - False

Answer : A

Explanation

Q 7 - Which of the following is used to generate static report that contains planning run material wise and it displays time of MRP run at the top?

A - MRP List

B - Stock/Requirement List

C - Long Term Planning

D - All of the above

Answer : A

Explanation

MRP List is used to generate static report that contains planning run material wise and it displays time of MRP run at the top.

Use T-Code MD05 or go to Logistics → Production → MRP → Evaluation → MRP list

Q 8 - To perform Goods issue reversal, what is the movement type?

A - 261

B - 262

C - 263

D - 264

Answer : B

Q 9 - A Storage location is defined as location where materials are stored in plant?

A - True

B - False

Answer : A

Q 10 - Which of the following Transaction can be used confirm a Production Order and for Goods movement?

A - CO01

B - CO02

C - CO15

D - MD16

Answer : C

Explanation

To confirm Production Order, use T-code: CO15

You can perform following activities −

  • Generate confirmation document
  • Consume raw materials or semi-finished goods
  • Good receipt of finished goods or semi-finished goods